PP: Capacity levelling - Time Profile

Former Member
0 Kudos

Hi Gurus,

When I run transaction CM29 and enter work center & plant , system gets hang . when I go to change profile button and change start date 2- (01/08/2007) to 10 - (01/12/2006), it works fine.

We have Time profile : SAPSFCZ002

Evaluation Period:

Entry Type: J

Start Date : 2- (default - which doesn't work)

Finish date : 4 (29/02/2008)

Planning Period:

Entry Type: J

Start Date : 1- (01/09/2007)

Finish date : 4 (31/01/2008)

Can anyone explain me? Whether it is bug or should use different profile?

Thanks in advance

Shiv

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please chech the following.

1. The evaluation period must be smaller than or equal to the database read period.

2. The planning period must be smaller than or equal to the evaluation period.

Regards

Kannan