on 10-08-2007 12:07 PM
Hi,
I need to append customer and material to the datasource 0CO_OM_WBS_1. They are part of 0CO_OM_WBS_6 for actuals.
It's for the key figure type 1001 "Revenue and Relevant Quantities" where I get the Actual values (10) from 0CO_OM_WBS_6 and the plan values (20) from 0CO_OM_WBS_1.
Have any of you created a enhancement of this type?
Regards,
Morten
If those are available for planning too then enhance 0co_om_wbs_1 otherwise you'd better put a filter in 0co_om_wbs_1 to extract plan only and combine this with 0co_om_wbs_6 for actual, you'll get faster loads too.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I would recommend you enhance the data source
By enhancing the extract structure. If the actual has
the fields you need, the planned should also have it, but
for any reason you don't have those fields, then there is
no solution other than enhancing it
Thank
Wind
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.