Transfer from DP to R/3

Hi Friends,

I am working on SCM 5.0 & ECC 6.0.

I want to transfer Forecast to R/3 as PIR.

Is this through CIF or creation of transfer profile & Publication settings are enough.

Can somebody pls tell steps wise process for transfer DP to R/3.

I have created Transfer Profile & did Publication settings and then execute the job.

But I didnt get it in R/3 MD63.

Pls help its urgent.

Points for sure.

Vishal..

Former Member
Former Member replied

there is no need of the any intergration model to transfer forcast as PIR to the ECC.

There is standard trx code for this.

<b>/SAPAPO/MC90 - Release Demand Planning to Supply Network Planning</b>

only thing imp in this transfer is, whatver the CVC's you are having in APO. like product, location needs to be in the R/3 system.

thats all.

pravin mukkawar