It is possible to put on the service order more than one work center ? or it must have just one work center (main work center )????????
Hi
Yes. We can use multiple Work centers.
Use separate Order Operations. Detail the project by reserving material
per operation and estimate time per trade group in that manner.
eg: Replace Pump with larger unit.
op 01 - Lock out and disconnect motor. EL - 1hr
op 02 - remove original pump assembly. MW x 2 - 1.5 hr (x 2)
op 03 - mount new pump and motor on base. MW x 1 - 4 hr
op 03 - - - etc.
Confirming each Order Operation as it is completed will compile great
history for future projects, and allow efficiency evaluation
<b>See related link -></b>
http://sap.ittoolbox.com/groups/technical-functional/sap-log-pm/work-center-on-service-order-530666
<u>For more details, please post your query in this forum link given below -></u>
Hope this will help.
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.