Hello!

I have a question for you.

I am trying to make a service order and i want to use two work centers , two activity types and two cost centers.

My problem is with the cost center.

When I am making DP90 I can see the cost center for each activity type - work center but in VA02 I have the same cost center for each component or operations(cost center for main work center , the one that I set in the header data of the service order).

What should I do to have the cost centers properly assigned ?????? It's very urgent.

Please help me!

Any help would be appreciated.

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question