Planned order scheduling

Hi,

I want to create a planned order which is planned automatically and be visible in CM01..How can i do this?

Thanks

Former Member
Former Member replied

Create in MD11, order type LA.

Schedule the planned order, if the master data is okay, system will scedule and you can see the details in CM01.

Message was edited by:

Rajesha Vittal

0 View this answer in context

Helpful Answer