Dears,

I have Planning scenario for final product and subassembly which is this subassembly a part of the final product in BOM

I work with strategy 11 for the final product , what is the strategy should be for this subassemply ?

I need to consider this parameter for subassembly strategy :

1- net requirement calculation

2- planned independent requirement reduction at GR of production order

Regards

Rami

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If you are not planning to sell the subassembly, you need not have any strategy for subassembly.

The requirements for subassembly will come by BOM explosion as dependent requirements.

Regards

YMREDDY

former_member182449
Participant
0 Kudos

Dear YMREDDY,

Thanks For Your Concern

I also need to plan for this subassembly PIR not depend on only the requirements from BOM Explosion

Regards

Rami

Former Member
0 Kudos

Hi

If you want net requirements unlike for the finish product, you can safely use startegy group 40.That will satisfy your other requirement .

Regards