conversion of planned order into prd order

Former Member
0 Kudos

Dear Gurus

Is it possible to convert planned order to prd order automaticaly ?Is there any setting in customising?

thanks

kk

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Kedar,

To my knowledge this is not possible in Standard SAP, probably a developing a conversion program using BDC/LSWM or New program copy of CO41 with option to run in background should do the trick.

Regards,

Prasobh

Former Member
0 Kudos

Hi

In Standard SAP there is no such possibility.

In real time normally it is not required like that.

why because ,after looking into the planned order, planner/scheduler should convert planned oirder into production order. to have a better control.

Planned order is one of the control step for proper scheduling.

I do nto think it is required.

If still business required to that you have to go in for customized programe with back ground scheduling.

Regards

YMREDDY

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As said by others its not possible to convert production order directly. you can do Collective conversion of pland order to production order by using the transaction CO41.

Thanks and Regards,

Satish