on 10-05-2007 9:29 PM
I have a material that is to be produced in another plant via a special procurement key. When a production order is created at times on MD04 I can see exceptions at the planning plant and not the delivery plant. Is there a way to make sure the planning plant displays the exceptions as well? Thanks in advance for any help.
I found the answer. Since planning is only expected to be done at the planning plant the rescheduling dates and exception messages only apply there. There isn't any config to allow the production plant to see the reschedule dates or exception messages.