We have several materials that have BOM's and both the components and the BOM material are stored in the same warehouse. The BOM's are simple kits that are manually assembeld or taken apart in the warehouse. I cant figure out how SAP should handel this assembling, i cant find any way other than a production order, and PP is not used in this system. I would like to use MIGO to do a posting change from the components to the BOM material. But i cant find any way to do multiple material to one material posting change only one to one.

Does any of the gurus have any hints or tricks or is it a PP order and implementation of PP that solves it.

in advance thanks