hi all,
when i am trying to create a sales order, its saying that wbs element is missing and the document is not getting saved. what is this wbs element and to which module it belongs.
can anyone help me.......
thanks in advance.
pavan
thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
<b>WBS is nothing but Work Breakdown Structure. It is mainly used in Project System (PS) module. Tcode : CJ20N</b>
For any project defined we must have at least one WBS. Within this WBS we can have networks. Networks are nothing but the series of activities. Material are used to perform the activities.
To explain in detail just consider one example:
Govt of India wants to have Roads to be build through out the India. So Project can be defined in sap as "Connectivity".
WBS can be roads within different states like Roads for Gujarat, Karnataka etc.. i.e. WBS Gujarat, WBS Karnataka etc.
We can define different networks for these WBS like Road Between Ahmedabad to Surat or Between Bangalore to Belgham.
For this network we can have many activities like Land selection, Land Preparation, Road Building, Final finishing etc etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.