on 10-05-2007 8:34 AM
Hi,
I would like to inform there is an issue in mismatch of assigned budget value in CJ33 wrt hierarchical report(S_ALR_87013558). Request you to suggest to fix the issue.
Thank you for your coopearation.
Regards,
Ranjan
Hi
I understand that u mean abot the assigned value in the report. If it is assigned value it has nothing to do with budget, assigned is equal to the sum of actual cost, commitment cost and remain order plan value. CJ33 is for budget releases and the better report for checking the releases is S_ALR_87013560.
If this is not the query, could u please elaborate ur query.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ranjan,
I suggest you to take a close look at note 178837 " Availability control: incorrect assigned value? ". It is a very good note that explains the difference between the <i>active</i> and <i>pasive</i> availability control and why differences can be found between the
info system reports and the budgeting transactions.
Hope this helps!
Regards
Martina
Hi Martina,
Thanks for your suggestion. I would like to inform, there is some discrepancy in S_ALR_87013558 report as rem order plan is consuming some kind of budget & the value is also coming in assigned value. Exmept cost elements has maintained for the desired cost elements of production orders (production orders shouls n't consume any budget in my case) as this should n't come under budget availability. Could you please suggest to remove the rem order plan coloumn from the report. I tried in the report painter & able to remove the coulmn but the budget is consumed by rem order plan. Request you to look into the matter & suggest to fix the isuue.
Thank you for your coopearation.
Regards,
Ranjan
Ranjan,
removing a column in a report will not affect at all at the values observed. Therefore,
it is unuseful to do it.
If there are inconsistencies in the assigned value, i suggest you to take the following steps:
1. Excute the report BPDIST03 via SE38 for the project in question.
2. Excute the tnrx CJEN.(Reconstruction of project information DB)
3. Excute the trnx CJBW.(Deactivate the availability control)
4. Excute the trnx CJBN.(Reconstruction of availability control)
5. Excute the trnx CJBV.(Activate the availability control again)
Hope this helps
Regards
Martina
Hai Ranjan
Could u explain the scenario. Cj33 - where the budget is assigned - whereas S_ALR_87013558 is just a report based on the assigned budget to a particular project. Check ur config settings.
ENJOY SAP PS.
Regards
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.