on 10-03-2007 3:39 PM
In CN41 and CN41N reports the plan and commitment values are not getting totaled up at the WBS element level
Is there any SAP note to be applied, pls guide
Hi,
Please check in your planning profile whether bottom up planning indicator has considered or not as this will sum up the cost from lower level WBSE.
Hope this will help you.
Regards,
Rakesh Pradhan