on 10-03-2007 8:25 AM
Hi,
We have a process where successful bids are turned into a global outline
agreements. GOA's are nicely distributed to the backend system (ECC), but
we also want to distribute the GOA information (contract number) into the
CCM. In GOA there is no such indicator as "distribute Contract to Catalaog"
(like the one in local contracts).
How is the distribution done in SRM 5.0 + CCM 2.0?
We have XI
Hi
1) You should configure XI to transfer Product Master and Contract from SRM to CCM. Please check the CCM Configuration Guide.
http://service.sap.com/ibc-srm
2) You can upload items from text file.
http://help.sap.com/saphelp_ccm20/helpdata/en/index.htm
You can also use SRM-MDM Catalog with SRM 5.0.
CCM has CAT(Catalog Authering Tool) and CSE(Catalog Search Engine). If you design the CSE in other client or other server, XI is required for publishing.
Use the "Publish Locally" option in the IMG, Cross-Application components -> SAP Catalog Content Management -> SAP Catalog Authoring Tool -> Specify setting for Publishing Catalog. So the CAT and CSE are same client. You do not need a XI for publishing.
You can distribute the GOA to CCM Catalog also. So that you can see all the Contracts on the CCM Catalog.
If you use CCM catalog from R/3 PM to create PO you can get the GOA data along with the products.
<b>Related links -></b>
Hope this will help.
Regards
- Atul