on 10-02-2007 3:10 PM
Hi!
In my parea ZPA_REG, i have 2 dataview. One is by week and the second one is by month. I enter 100 at month level for October 2007. Then, i go in the second dataview (week level) and i see
S40 25
S41 25
S42 14
S43 25
S44 11
My question is about S41 ad S44. For S44, since there are only 3 days for october it could explain the result. But i don't understand why for S42 the value is 14 .
The Time Stream ID (transaction /sapapo/calendar) is based on US calendar. Its calculation type is with gaps.
The storage bucket profile is by Day, Week, Month and year.
The time based disagregation for my KF is type P.
Can you help me please.
Thanks by advance,
LB
Dont think US calendar has holidays in that week of of October. I would go with the second suggestion given in the other response. Also check if this is a US calendar only behaviour or something that you see across the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for your answers.
I put type E instead of type P and it seems to be better.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1. check if there are any holidays in that week. looks like it could be 2 holidays there.
2. zero out all the values in the weeks and re enter 100. sometimes if there is a value already existing it will follow that proportion by default and not your planning area disaggregation type
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.