on 10-02-2007 3:16 AM
Hi,
My company want to give free goods in Bill of materials.But system is not accepting that.How can we do that?
I am getting the same problem with Material Determination and Free Goods combination.When i configure material determination for a material which is having free goods system is not showing...any idea?
Points for sure.
Hi,
The constraints for free goods in SAP are as follow
<u><b>Constraints</b></u>
Free goods is currently only supported on a 1:1 basis. This means that an order item can only be
the source of one free goods item. This means that agreements involving relationships such as
'Buy material 1 and get material 2 and material 3 free of charge' or 'Order material 1 and material
2 together and get material 3 free of charge' are not supported.
<u><b>Free goods is not currently supported in combination with material structures (e.g. product
selection, bills of material, variants with BOM explosion</b></u>).
Free goods is currently only supported for sales orders with document category C (not for
quotations, for example).
Free goods is not currently supported for deliveries without reference to a sales order.
Free goods is not currently supported for make-to-order production, third-party order processing
and scheduling agreements.
Hope it helps you.
Regards,
Sarosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.