Good Day.

When I am changing a date in the schedule line. everything resets back to start date.

For example:

a> 10/1 x 5000

b> 10/15 x 5000

c> 10/30 x 5000

I just want to change the date of b> from 10/15 to 10/10, but everything just resets back to zero, such that i have to re-enter 10/1 & 10/30 again.

What should I do to prevent that?

Let me know...

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

this can be happening if none of the schedule lines have been met.

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks for the inputs

rmazzali
Active Contributor
0 Kudos

do not use a standard order to manage schedule lines. Use scheduling agreements instead, they are much more flexible.