Hi
Could any one pls clarify, what exactly the criteria for system (RFC) to replicate the data to R/3 from SRM, to be more clear if I create a PO in SRM and got replicated to R/3 and GR made also. Then if I change the PO in SRM while GR existing (Follow on documents) , then does the changes will replicate to R/3 or not?
We have a case where in some times some changes in documents are not replicating to R/3 , but yes some times. Hence I would like to know, are there any particular criteria for replication if yes, please let me know what settings need to be checked.
Thanks & Regards
Kiran Kumar
Hi
Which SRM and R/3 versions are you using ?
You could manualy re-transfer the local SRM PO with function module BBP_PD_PO_TRANSFER_EXEC using the GUID of the PO. You will find the GUID when you run transaction BBP_PD with the object ID of the PO and BUS2201. To find out the cause, you could debug this function module to the call of BBP_PO_INBOUND function module in the backend and check the return table.
<b>Please refer to the liks as well -></b>
Check out this BADI "BBP_ECS_PO_OUT_BADI". It will help you in determining which data to be sent to back end (it will override the standard).
Do let me know.
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.