1. Execute SM36 Transaction
2. Enter Job Name & Click START CONDITION
3. Click Period Values & type 12 in Months
4. CLick SAVE
5. Enter Schedule Start Date & Time
6. Click Save
7. Click on STEP
8. ABAP Program Name
9. enter program name & Variant if any
10. CLick on SAVE.