09-26-2007 8:24 PM
Hi ISU Experts,
I have a following problem in ISU,
When create a Move In or a Move out, the system should automatically create a Meter read Order and a Service Order in the Background.
Same case is applicable for the Aperiodic meter read order, whenever I create a Aperiodic meter read order, the system should create a service order/ notification automatically in the background,
As mentioned above, In both the cases no service order/notifications is getting cretaed.
I have maintained the SPRO settings for Aperiodic meter reading and for Move in and Move out , the service order creation checkbos is checked.
Please anybody can throw some light, help me out what may be the problem, or any other SPro settings are to be maintained, any enhancement has to be done.
Your inputs will be highly appericiated .
Best Regards
Suresh
07-06-2009 6:51 PM
Hi,
I am stuck with the same issue. I have checked the check box to create service order/notification from the meter reading order. Please let me know if you have found any resolution
Thanks,
Dhana