Factory Calendar transfer

Former Member
0 Kudos

Hi,

i want to know if we can transfer Factory calendar from ECC to APO. is it possible?

and if yes, how to do that?

if anybody can advice on this topic!

Thanks,

Regards

Jignesh.

Accepted Solutions (1)

Accepted Solutions (1)

srinivas_krishnamoorthy
Active Contributor
0 Kudos

run report RSIMPCUST to do this transfer.

Former Member
0 Kudos

Thank you Srinivas for your help,

could u please tell me how to display data after running this report!

Thanks

Regards

Jignesh.

srinivas_krishnamoorthy
Active Contributor
0 Kudos

The report takes you to the same path as mentioned by Harish.

Try running the report with the Factory Calendar checkbox on. We run the report daily and there are spools of the job that show up. So try running it in background and see what you get in the log.

Answers (1)

Answers (1)

Former Member
0 Kudos

am not sure if the previous reply takes you to the same path ...

Go to RSA1

choose Source systems tab on the left

Right click on connected your R3 system

there is an option that is "import global settings" or something like that (dont have an R3 connection right now)

you can bring in a couple of things - one of which is R3 calendar

Former Member
0 Kudos

Thanks Harish,

I have followed your steps but as i asked Srinivas, how to display this data??

if you can give me advice on this!

Thanks

Regards

Jignesh.

Former Member
0 Kudos

not sure if you will get any log... i havent tried it in SCM 5.0 but if it runs successfully you can be assured the calendars have been updated

you can compare the relevant calendars from APO /SAPAPO/calendar with calendars in R3