on 09-24-2007 1:31 PM
I am using APO DP V5.
I need to understand how forecast strategy 60 (copy history) works.
Suppose I have a three year forecast horizon.
Can I use this to copy from last year's history into <u>each</u> of these 3 years?
Thanks,
Bob Austin, Atos Origin
Hi Bob.
The answer to your question is no. 12 months of history will only generate 12 months of forecast.
I would suggest that if this was a requirement then a macro could be used to generate such a forecast.
Hope this helps.
Mark