Please can you tell anybody checkin / checkout of complete process step by step.

I’ve idea but I m looking for exact step by step

I am able to do up to checkin.

I don’t know how to checkout of same DC.I want to some modification again I want to checkin.

Please help me out.

Thanks n Rgds

-AW

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

In simple terms I can put it this way

1) First you need to verify if you have the checkin/checkout permissions.

2) Go to DTR perspective select the SC/DC which you want to modify, right clich and sync the sources

3) Again right click on the selected the DC you want to edit and then select Edit,

It will prompt you for an activity name. Enter the activity name

4) Once you successfully check out you will be able to see your newly created activites under open activity. Do the necessary changes and the check in the activity from the open activites view.

5) After successful checkin of your activity you will be able to seee it under closed activites following which you shall activate your activty.

Additionally you may refer the link below for clean steps:

<a href="http://help.sap.com/saphelp_nw04/helpdata/en/88/cb0b405bacdd5fe10000000a155106/frameset.htm">http://help.sap.com/saphelp_nw04/helpdata/en/88/cb0b405bacdd5fe10000000a155106/frameset.htm</a>

You may also go through the topic "Editing development components" under the topic "Working with components". Hope this helps.

Akshatha