on 09-20-2007 8:22 AM
Hi,
This is regarding Transaction DB13(DBA planning calender:Maintain)
which is taking long time to initialize i mean to display the DBA
Planning calender screen. This is happening only with DB13 other
transactions are executing very fine.Iam working on sap4.6C, windows
2003 server and oracle 9.2. I would appreciate if you can guide me in
resolving this issue.
Waiting for your reply.
Regards
Hi,
thanks for ur replies...
But can i ask you something ....
Why this is happening only with my Development server because i have the same parameters set for my production server( Every thing is same in my PRD & DEV servers) as well am not facing any problem over ther for DB13.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes i have posted the message to marketplace and this was there reply.
As first step, please make sure the database parameters are set as
per note 124361. If you confirm that these are set correctly, please
provide a html output from TX ST04 -> detailed analysis -> parameter
changes -> active values.
Secondly, create new statistics for table TBTCO using transaction DB20.
I did as they said.. but the database parameters thing i dont know that much.
You know what there is no database admin so i only need to resolve this issue.
Hope you can help me out in resolving this issue....
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When iam executing DB13OLD it is saying transaction does not exist.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
DB13OLD is a netweaver 2004s with support packs level 12.
this is not your system version.
I would open a SAP message at http://service.sap.com/message
when you fix the problem, tell us what you did because you are not the only one complaining about this issue.
Hi,
Iam working on SAP 4.6C , windows2003 server and oracle-9.2 versions.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for replying.
I have performed the brconnect command you have mentioned but still its the same. Transaction DB13 is still taking time to display the calender screen.
Please help me out in this regard as this issue iam facing since long time.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there thanks for your reply..
When am executing Brconnect for SDBA* it is saying SDBA doest not exist .
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your kind reply
I have run both commands but still its the same.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in DB13, run job CLEANUPLOGS
or at OS level:
brconnect -c -u / -f cleanup
then, update stats:
brconnect -c -u / -f stats -t TBTCO -f collect
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.