Free capacity not consumed

Hello Gurus,

My forecast requirement date was created 08.10.2007 with a quantity of 128 pcs. I have 500 pcs available for consumption. I was wondering why was the demand element did not consume the stock and created a planned order with date 17.10.2007.

Please advise. Thanks

Former Member
replied

please check if you have any kind of horizon that is preventing it from creating anything before 17th (if you try the same now is it still 17th? or has it moved?)

also pl check if your stock is not blocked or restricted and is not pegged by any other requirement

Also pl check the stock tab in RRP3 to see if there are any issues appearing