In MD04 Stock Requirements for two plants 0011 and 0012. Plant 0012 has a Stock Transport Purchase Order STO001/10 where it is buying from the sending plant of 0011 and an arrival date of 09/21/07. Plant 0011 has the demand side of the Stock Transport Purchase RelOrd saying it needs to Ship on 09/10/07(so it gets to plant 0012 by 9/21/07.
Next, I run transaction VL10B to create a delivery in plant 0011 so I can get ready to ship the goods.
Now, when I look at Stock Requirements in the shipping plant (0011) you will note that the delivery say the shipping date of 9/20/07. The delivery date changes to the date of the receiving plant Stock Transport Order i.e 9/20/07. In plant 0012 the PO will show date 9/21/07 because it has 1 day goods receipt time in the material master.
<b>The MRP element RelOrd date changes when the delivery is created before doing PGI why the date changes in MD04???</b>
Thanks,
Suresh
Suresh,
Please Refr OSS Note-25444.
This deals with the inconsistencies with MD04 & Actual Placed orders.
REWARD IF U FINDS THIS AS USEFUL...
Regds
MM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.