ASAP (AcceleratedSAP) is a step-by-step methodology for speeding up the implementation of an SAP R/3 system. The components of ASAP, which can be used together or individually, are called accelerators. Accelerators are based on the best practices of SAP customers from around the world and consist of a number of templates, questions, and scenarios that require user input to help the user determine the best way to implement their R/3 system. According to SAP literature, ASAP can reduce the time required to implement an R/3 system by as much as 50%.

ASAP is shipped automatically with every R/3 delivery and upgrade. There is no charge for ASAP.

here is the diffrent division of ASAP...

ASAP METHODOLOGY

Phase 1

<b>Project Preparation -</b> The primary focus of Phase 1 is getting the project started,identifying team members and developing a high-level plan.

Phase 2

<b>Business Blueprint -</b>The primary focus of Phase 2 is to understand the business goals of the company and to determine the business requirements needed to support those goals.

Phase 3

<b>Realization :-</b>

The purpose of this phase is to implement all the business and process

requirements based on the Business Blueprint. You customize the system step by step in two work packages, Baseline and Final configuration.

Phase 4

<b>Final Preparation -</b> The purpose of this phase is to complete testing, end-user training,

system management and cut over activities. Critical open issues are resolved. Upon the successful completion of this phase, you will be ready to run your business in your productive R/3 system.

Phase 5

<b>Go Live and Support -</b> Transition from a project oriented, pre-productive environment to a successful and live productive operation.

For more info have a look.......

http://www.sapfans.com/sapfans/asap/be_01_e.htm

regards

biplab

Former Member
0 Kudos

Hi

For more

Thanks

Former Member
0 Kudos

Hi

Hey are you asking for the Implementation methodology used by SAP-XI.It is known as

AcceleratedSAP (ASAP) Roadmap.

The ASAP Methodology has five phases:

1. Project Preparation – project formally initiated and planning well under way.

2. Business Blueprint – project team gathers requirements and conducts conceptual design of the solution.

3. Realization – system solution is built and integration tested, end users trained

4. Final Preparation – final check before cut over to new system solution

5. Go Live & Support – solution confirmation, on-going support in place and project closing

The ASAP Implementation Roadmap for Exchange Infrastructure provides guidance for the implementation teams embarking on implementation project of SAP XI Solution.

http://www.sap-basis-abap.com/sapgeneral/what-is-asap.htm

Refer link below for a brief ASAP stages

ASAP SAP IMPLEMENTATION

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/SVASAP/SVASAP.pdf

http://media.sdn.sap.com/html/submitted_docs/Implementation_Roadmap_XI/index.htm

Thanks

Former Member
0 Kudos