how long it will take to develope one Interface?
Depends on the complexity of the interface.
It might be based on the following factors;
1. Mapping program used.
2. involvement of 3rd party adapters.
3. custom coding to be developed.
4. adapter modules to be developed
etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It all depends on the complexity of the scenario and your expertise in the field.
Suppose you need Java Mapping or ABAP Mapping for your scenario which you are not aware with,then definitely it will take time.On the other hand if it requires simple graphical mapping ,the scenario will be finished in seconds.
Thanks
Hi Monika,
Development Duration of one interface depends totally on requirement like.
Type of Mapping(Java, ABAP, XSLT, GM) (no of input and out fields and trasformation logic)
DT need to create (XSD is not available)
BPM is involved or not.
Numbers or receivers...Adapters..Need Proxy or not..
Also as per good companies, Min 15 days are required to built simplest interface...even you can develope it in 1 day;-) But 15 days minimum estimation.
It required self review, peer review, SME review etc..Also development is not complete till interface is not tested with real test data;-)
<b>Thanks & Regards,</b>
Farooq Farooqui.
*Rewards points if you find it useful*