on 09-14-2007 1:21 PM
Hello,
I run Location Heurisitc and it creates planned STR ( goes to Planned Receipts Key Figures ) .
Then I run deployment and Deployment creates confirmed STR ( goes to Distribution Receipts Confirmed Key figure ). STR is not converted to STO but it is in R/3.
I run again Location Heuristics but Deployment confirmed STR is not touched. I was expecting it to be deleted as it is still STR and not STO.
Can someone explain this behavior ?
Thanks.
Quick question: in your SNP Global settings, what entry do you have for "Heu: Order Update" parameter ? Is it delta or complete ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not sure whats going on. I have the same setup, just that we run CTM instead of Heuristics that gets rid of all deployment plans that are not converted to order. If you are planning to run the schedule in batch, you always have the option of deleting the deployment orders selectively through RLCDELETE transaction or through a macro.
Ketan,
Check whether SAP note 974211 is missing in your system.
Regards,
Chava
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.