If I create a bid invitation via transaction BBP_BID_INV that doesn't have reference to a shopping cart, where can I enter cost assignment data to create afterwards a purchase order document in the back end system?
thank you,
joseph
Hi,
If you create a bid invitation from scratch (without a former SC), there is no standard way to have an ECS PO : your PO will stay local (standalone) and will never been replicated.
There is no cost assignment in the bid invitation !
Kind regards,
Yann
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I would like to post the system behaviour which I can see on my system .
If I create a fresh BI in SRM (without ref to backend PR) , in the resultant CLASSIC po the AAC is taken as K by default and is changable.
This is in line with the behaviour of SRM for PR transfer from backend.
i.e. when an ECC PR with AAC =N or F is transferred to SRM sourcing,
SRM resets the AAC to K
if you need a realistic one you need BADI BBP_BADI_EXTREQ_OUT
BR
Dinesh
(Reward if helps )