Can somebody explain wat is the diff between Reservation to ntwrk and Reservation to WBS in material procurement.
What all are the impacts of the same with reference to other transaction?
Regards,
Deepak Joy
Hi,
You create a reservation for network, when you wish to maintain plant stock for that material. In case of reservation for wbs, you maintain project stock for that material.
http://help.sap.com/saphelp_47x200/helpdata/en/4c/227b7346e611d189470000e829fbbd/frameset.htm