Hi,

We are using SAP XI SP19 with 2 server nodes. We have a list of communication channels that are supposed to go down for a specific interval everyday.

This is accomplished with the help of availability time planning .

The issue is that the availability plan does not work as scheduled in one of the nodes and seems pefectly fine on the other... What could be the reason ?? Please let me know as to how can this issue be solved.

I have gone through the note 1071144 and we have the patch higher than suggested here.

regards,

Raghu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

solved by increasing the value in clustercommunicationTimeout parameter in VA