Hi
Refer below steps for STO
<b>Configuring the Stock Transport Order </b>
Orders can be done by:
- Configure using transaction OMGN.
- Depending upon the sending and receiving plants, maintain sales organization and customer data in customizing.
- Maintain the supplying plant as a vendor and attach the plant to the vendor in the Vendor Master.
- Material type has to be HALB or HAWA.
- Ensure that the company with sales Organization has a plant to take care of stocking.
- The PO used is NB and not Stock Transfer PO.
Configure SD for inter-company billing to enable picking up the pricing procedure for billing.
- Carry Out delivery through process delivery due list and billing through process billing due list.
Otherwise, You need to configure your Stock Transport Order settings for your Cross-Company:
Business Transaction to work.
1. Customer No. for the Goods Receiving Plant - OMGN
2. Availability Check- Checking Rule (if necessary) - OMGN
3. Assign a Delivery Type for the Delivering Plant - OMGN (for Stock Transport Orders, NLCC)
4. PO type (which i belive you have done) - OMGN
5. Assign Vendor No. to the Supplying Plant (done) - VK02
6. Assign Customer No. to the Purchasing Plant for the Inter-Compnay Invoice (but you need to assign this to the Sales Organization pre-assigned to the Purchasing Plant),
IMG-SD-Billing-InterCompany Billing-Define Internal Customer No. by Sales Org
***and by the way for the Invoice to work between Cross-Compnay Plants, you need also to have a Sales Org for the Supplying Plant and a Pricing Determination Procedure.
Configure Intercompany Stock Transport Order
Material should exist in both the plants (Delivering & Ordering),
Internal customer should be assaigned to the ordering plant ( MM -> Purchasing -> Purchase Order -> Setup stock transport order -> assign the internal customer to the ordering plant and assign the Sales area of the internal customer.
Assign its Sales area to the delivering plant
Assign the document type and Delivery type NB and NLCC
Assign the Supplying plant --> Receiving Plant --> NB
Take the delivering plant and assign the sales area.
Vendor master has to be created and assaign the supply source ( Delivering Plant).
Create a puchase order ME21N ---> Save
Delivery VL10 G ---> Calculation rule (appropriate) --> Assaign the purchase order number here and execute.
Select the Delivery creation line and do the back ground process.
Start the log display and see the delivery document number by the documents button
Goto VL02N --> do picking and PGI --> Then do the MIGO with respect to the delivery document.
Billing (Intercompany pricing conditions should be set).
Refer the links
http://mailman.mit.edu/pipermail/sap-wug/2001-May/001973.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please read the <b>rules of engagement</b> before posting.
- <b>Do not ask to send you an email.</b>
The question you ask and the solution to it is often also interesting for other users of the community. If you ask somebody to send you the answer per email, you deprive others of also learning to know the answer. Therefore any requests for sending material or answers to an email address will be modified by the forum moderators.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.