on 09-04-2007 8:13 AM
Hi Guys,
I have scenario here
WBS Element--> User status phase I WIP, Phase I Complete, Phase II Wip....
Network Header Phase I
Activity 1
Activity 2
Activity 3
.
.
Activity x--> When confirmed should trigger WBS user status to Phase I complete
Network header Phase II
Similarly.
How do i do this in PS? I need the WBS user status to be triggered Automatically from activity confirmation.
Regards,
Paval.
Hi,
I think u can not automate this user status in a std system.
However u can set the initial status & hi & low status for chenging the status manually.
Check with the ABAPers if it can be done.
sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i did the same through an enhancment
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
I think it is possible throuugh Event Linkage Method( SWETYPV transaction), can get help from your ABAPer/workflow guy.
I am just giving hints which may help your ABAPer .
Get Business object for Network BUS2002,
Check for Event of Confirmation if not available , create the event for custom Business object (copy of BUS2002).
Maintain this through SWETYPV transaction,
in Detail level enter Receive function module that should consist of actual logic.
Thanks
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.