Did you mean: 

Automatic trigger of WBS user status

Former Member
0 Kudos

Hi Guys,

I have scenario here

WBS Element--> User status phase I WIP, Phase I Complete, Phase II Wip....

Network Header Phase I

Activity 1

Activity 2

Activity 3

.

.

Activity x--> When confirmed should trigger WBS user status to Phase I complete

Network header Phase II

Similarly.

How do i do this in PS? I need the WBS user status to be triggered Automatically from activity confirmation.

Regards,

Paval.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I think u can not automate this user status in a std system.

However u can set the initial status & hi & low status for chenging the status manually.

Check with the ABAPers if it can be done.

sunil

Answers (2)

Answers (2)

Former Member
0 Kudos

i did the same through an enhancment

Former Member
0 Kudos

Hi ,

I think it is possible throuugh Event Linkage Method( SWETYPV transaction), can get help from your ABAPer/workflow guy.

I am just giving hints which may help your ABAPer .

Get Business object for Network BUS2002,

Check for Event of Confirmation if not available , create the event for custom Business object (copy of BUS2002).

Maintain this through SWETYPV transaction,

in Detail level enter Receive function module that should consist of actual logic.