When i put down payment here in VA01 billing plan (WBS element linked)
For e.g., PR00 = Rs. 1,00,000
<b>Billing Plan</b>
30%, 40% and remaining after the receipt of material at client's site
but commercial and excise invoice will go with the material with 100% value
1.30 % value - 30, 000 Billing Type FAZ - Down payment Request
2.40% value - 40,000 Billing Type FAZ - Down payment Request
So now,only 70% of the PR00 is recieved
But in the sales order if i put 30% ..it is talking 30% of net price(PR00 + EDCESSCST/VAT+ Service Tax) and the same case with 40% DP also.
when i create a down payment request, AZWR condition type is throwing with the information message, saying that " <u><i>Downpayment value is higher/lower than pre-set value"</i></u>
customer down payment is normally some % of the agreed price(PR00)
how to tell to the SAP system that when i create FAZ it shud take % of PR00 and When I do F2 invoice(1,00,000 + ED+Taxes) it shud take everything into account?
Plz help me.
Regards,
Anbu
done
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.