on 09-02-2007 2:56 AM
Could some one guide me with XI Implementation Methodology Worksheet
Please note I have visited the following two areas, so please avoid them
/people/michal.krawczyk2/blog/2005/04/09/xi--saps-document-templates
Hi Jenni,
Implementation ..
1.Project Preparation and 2. Business Blueprint are the key responsible for Architect and Team Leads.Here they prepares the complete technical documentationsfor all the interfaces depending upon the requirements of the client.
In realizaiton he will develop all the interfaces. Once you develop you will move all the objects to QA and then in prod.
If there are any changes you will make in dev and move once again in QA and prod in Final preparation.
During Go live and support you will monitor all theinterfaces. If they have any issues you will resolve them.
For documentation about XI interfaces see the below link
/people/krishna.moorthyp/blog/2006/07/29/documentation-html-editor-in-xi
Check this link given below...
http://service.sap.com/asap -> ASAP Implementation Roadmap for SAP Exchange Infrastructure
Hope it helps..
Kumar.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
http://service.sap.com/asap -> ASAP Implementation Roadmap for SAP Exchange Infrastructure
1. A blueprint of the landscape
2. A scope of the project
3. Information on the systems involved
4. A check on whether 3rd party systems will need to have 3rd party adapters.
5. The preference of development - with BPM or not/the mapping preferences of the customer. etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.