Schedule Agreement

Former Member
0 Kudos

Hi Gurus,

Can anyone please explain me the process of Schedule agreement?

what is the difference between sch agreement with delivery order and sch agreement with delivery ie LZ and LZM document type?

also can u please explain me the difference between Forecast Scheduling and JIT scheduling in LZ document type?

Please reply at the earliest.

Thanks and regards

Anil

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi

Creating a Scheduling Agreement

https://www.sdn.sap.com/irj/sdn/wiki?path=/display/erplo/16FieldsDescriptioninPricing+Procedure&

Analyzing & Copying Scheduling Agreement

http://help.sap.com/erp2005_ehp_02/helpdata/en/45/f9a69036035f4be10000000a114a6b/frameset.htm

Processing Scheduling Agreements

http://help.sap.com/erp2005_ehp_02/helpdata/en/bd/1850f298a911d194fc00a0c9306667/frameset.htm

Controlling Scheduling Agreements

http://help.sap.com/erp2005_ehp_02/helpdata/en/93/7439ee546011d1a7020000e829fd11/frameset.htm

Example Data : Scheduling Agreements

http://help.sap.com/erp2005_ehp_02/helpdata/en/8a/815cc3b36211d188e70000e8216438/frameset.htm

Standard Agreement for Settlement Scheduling

http://help.sap.com/erp2005_ehp_02/helpdata/en/d0/235540e4c79354e10000000a155106/frameset.htm

====

Use the T.code VA31 (and choose Scheduleline agreement) :

This agreement lets you to predetermine scheduling of different materials with in a given period of time (This is same like the other contracts).

First enter the material with quantity say for example Material 1 Qty: 40, go to Edit from the menu >> Item >> Schedule line

There select within the time period defined two dates, say for example on 12: 01: 2005 20 quantity and on 13: 01: 2005 another 20 (The qty has to be same as the one in the sales order) .

Once this is done you have created a schedule line agreement.

Call this agreement in your sales order (with reference) and use them.

Note: You will be able to deliver only 20 qty on the 12th and 20 qty on the 13th, even though the sales order is for qty 40

Reward if Useful

Thanx & Regards.

Naren..

Former Member
0 Kudos

hi

anil mail sent regarding scheduling agreements

regards

Former Member
0 Kudos

1.An outline agreement that is created for one or more materials and outlines the overall expected quantity of the material(s) to be delivered to the customer over a specific period of time.

Use

The scheduling agreement is used as a basis for delivering a material. The customer sends in scheduling agreement releases, referred to as delivery schedules, at regular intervals to release a quantity of the material.

2.

You create a special type of scheduling agreement on which to base delivery orders. These scheduling agreements contain forecast delivery schedules with fields specific to delivery order processing. The scheduling agreement and forecast delivery schedule contain all the background information necessary (such as materials and quantities) to create schedule lines in the delivery order.

Features

The standard systems contains several new features specifically for processing delivery orders:

Scheduling agreement type LZM

Item category LZMA

Copy control from scheduling agreements to delivery orders

You can copy items into the delivery order with reference to their related scheduling agreements. Choose Sales ® Maintain copy control for sales documents in Customizing for Sales and Distribution. Use target document TAM and source document LZM.

LZ - Scheduling agreement with delivery schedules