Hi Guys,
Basically i am not expert in APO, can any one give me exact difference between Heuristic run in APO and MRP in R/3
Also just to confirm with is deployment in APO is transfer of requirements from apo to R/3 like planned order
or my guess is totally Wrong
Thanks in advance
Raj
Heuristic in APO is a broader set of algorithms for doing production planing and scheduling in APO. There is at least couple of Heuristics SAP_MRP_001/002 which logic wise is the same as MRP Run in R/3. Likewise SAP_PP_002 does basic planning for standard lots much like R/3 MRP run.
However there are many more logic possible with heuristics in APO for production planning and scheduling which can be viewed in SPRO >> APO >> Scupply Chain Planning >> PPDS >> Heuristics >> Maintain Heuristics
The second part about deployment - the statement is bit ambiguous. Deployement is a functionality of Supply Network Planning module in APO. Requirements (PIRs) from APO can be sent to R/3 directly from Demand Planning module.
But if you do planning in APO-PPDS (Production Planning Detailed Scheduling) then against the requirements, receipt elements - Planned Order (for in-house produced products) or Purchase Requisition (for externally procured products) are generated. These can be immediately transferred from APO to R/3 or can be transferred only after conversion to firm orders i.e. Production /Process Order and Purchase Orders respectively. This is controlled in the PPDS Global Paramaters.
Hope this helps.
Thanks,
Somnath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.