on 08-28-2007 3:46 PM
Dear SRMer's,
System Info SRM 5.0
I have scheduled BBP_GET_STATUS_2 and CLEAN_REQREQ_UP to run every 1 minute.Both jobs are in released status
Now I have a requirement to change to frequency to every 5 minutes as I am getting Internal spool errors. When I select the job to change the frequency, I get the message: 'Job not modifiable' in the status bar.
Please let me know the procedure for modifying a released job.
Thanks in advance.
Points will be rewarded.
Best regards,
Bob.
HI BOB
Can you cancell both the Jobs when they are in Release status
And then Reschudle new jobs with a new frequency....
Schedue BBP_GET_STATUS_2 first and subsequently Schedue CLEAN_REQREQ_UP .
regards,
Nimish Sheth