Updating the status in R/3

Former Member
0 Kudos

Hi All,

After creating the time & material confirmation, when I synchronise the data does not get updated in the back-end. Can anyone tell me whats the reason behind this?

Thanks in Advance!

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Can you plz tell me what is the error/warning in middleware worklist(merep_mon)?

Some times, Mobile client timezone and back-end timezones can be different...

In this case, future times in "Time confirmation" will not be posted(unless customization allows)

Best Regards.

Subhakanth

Former Member
0 Kudos

Hi,

Many thanks for the quick reply.

My error is as folllows;

-Return code from RFC BAPI Wrapper call:Actual date(s) is in the future (check parameter

-Return code from RFC BAPI Wrapper call:Confirmation data are incorrect

-Return code from RFC BAPI Wrapper call:Actual date(s) is in the future (check parameter

I did check the system timing settings and the device time settings. They are CET and timings match.

Pls comment!!!

Thanks & Regards

Kanwar!

Former Member
0 Kudos

Hmm...it's bit strange...

Can you please check the time in merep_mon to confirm whether it is the same as the one you have given in Mobile ? This is to confirm whether Mobile is sending the right time.

Best Regards,

Subhakanth

Below is FYI...

if you want Time confirmation in future, goto this customization

Plant Maintenance and Customer Service

Maintenance and Service Processing

Completion Confirmations

Define Control Parameters for Completion Confirmations

For plant and order type combination, in checks subscreen, you can flag "Date in future".

However it is recommended if the technician who does the time confirmation is in a different timezone.

Former Member
0 Kudos

Hi,

It worked!

Many thanks. It was time zone problem. Now I have set same time zone settings for both the servers.

Thank you once again for your valuable information.

Regards,

Kanwar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kanwar,

Kindly look into MEREP_MON (Worklist), check if the record is in waiting state.

In worklist, you can figure out..what could be the problem.

Kindly try this.

Cheers,

Karthick

Former Member
0 Kudos

Hi,

Many thanks for the quick reply.

My error is as folllows;

-Return code from RFC BAPI Wrapper call:Actual date(s) is in the future (check parameter

-Return code from RFC BAPI Wrapper call:Confirmation data are incorrect

-Return code from RFC BAPI Wrapper call:Actual date(s) is in the future (check parameter

I did check the system timing settings and the device time settings. They are CET and timings match.

Pls comment!!!

Thanks & Regards

Kanwar!