Dear SAP gurus,

We are using SRM server 550 with SP8, and using extended classic scenario. I see there is this one button "complete" in the PO. From what I see from other posts in SDN this button is useful to release the commitment for PO though the PO has not been fully confirmed/receipt.

I try to do this. We applied notes 1066895 to make sure the "complete" button works and then create a PO and approve it. The PO goes to backend and create some commitment. Then I click "Complete" and the status is changed to be "transaction complete" then when I check there is no change happening for the commitment related to this PO.

So what is the exact use of complete button? can it really release the commitment? Or do i miss something??

Best regards,

Yosea

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sibero,

Plz check this already answered thread and assign points if it clarifies your query.

Rgds,

Teja