on 08-24-2007 2:39 AM
Dear Basis gurus'
Customer using separate back up tool for backing up the back up folder. Is it required to schedule disk back up through DB13 or ask them to copy directly the data files on incremental.
Kindly help me
Regards
Joseph
Hi !
If you use a partial data backup as your daily backup, you must perform a
complete data backup at least once a week. There must be at least four
complete data backups contained in the backup cycle.
The log information should be backed up at least once a day. SAP recommend that you always have two different backup media containing the same information.
Perform a data and log info backup with verification of the backup media
at least once in the backup cycle.
You can use DB13 to schedule this, or any other solution (ex crontab)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
what tool are they using. is it as SAP agent for backup tool?
If so, it must be still using brbackup, so, adapt parameters in iniSID.sap and schedule your job from DB13 as any normal backup.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.