Scenario:

Requirements are not getting generated because the Material master was maintained with KP, which is no availability check. Now we have changed the availability check to 2, which is individual requirements.

Now for new Scheduling agreements requirements are getting generated, however for old Scheduling agreements requirements are still not getting generated.

Anyone can suggest solution, so that for we can generate requirements for old Scheduling agreements as well.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I dont think there is a way to generate requirments for old scheduling agreements that were created when the master data was maintained with KP.

If you add new line items to the existing scheduling agreements then the requirements will be generated for those,but for line items already existing,I guess there is no way to have requirements triggered for them.

<b>Reward if helpful.</b>

Thanks

Former Member
0 Kudos

Thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

its not only 02 but also Pd in mrp type hope u have also configured the TOR settings

anyways to generate requirments of old itme

just open tht order va02

go to scheduleline tab in item level

and top ther is this icon like a balance one./....

there are ikons at top 1) delete icon

2) ducment flow

3) item output overview ( with a circle and paper)

4) item availability ( like a balance )

click on this ikon save and go to md04 and check ur requiements wld b transfered