on 08-23-2007 10:39 AM
Dear Info,
kindly tell me what are the reports which can give description of downtime.
Regards
hi agha,
you can use the MCI4 and also see the path below
plant maintenance.>information systems>plant maintenance information system
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear friend,
thanks for the reply, previously you replied about the work centers that i have to give the production work center if i want pp pm integration. i achieved that by your guidance. but one question comes to my mind.
if i am giving pp work center for my operation then how will i give pm work center and how will i know that which of my work centers are free or busy.
Regards
Agha Khurram Shah