Hi,

Can anyone tell me the Sales flow happening through project systems?How the delivery happens?Does it happen through VL01N or through PS ie CNS0?

Kindly reply

regards

Somnath Chatterjee

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

I understand that the delivery of the material will be through PS.But my sales order is not getting updated when delivery is happening through PS.It still shows the status as open.

Kindly suggest.

regards

Somnath

Former Member
0 Kudos

Hi,

Project is created using CJ20N and then the WBS and networks are created. The sales order is created and the WBS element is assigned in the account assignment tab of the sales order.

The materials are added onto the network and the delivery is done on the project using CNS0.

The rest of the process is the same except that if there are activities involved in the project then we do CATS reporting and costing.

Hope this helps.

Former Member
0 Kudos
Former Member
0 Kudos

Hi

As per my knowledge there is no difference for Project sales, only in Pricing Procedure Determination we have include the document pricing procedure as P (Project Sales).

refer the sdn link below