Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Re-order point planning

Dear Sir,

We have configured Re-order point planning. Accordingly we have created

the MRP controller and updated the material master (812 materials) with

all the values required for re-order point planning.

With all these settings, system is not running planning after executing

MD01 (total planning), only planning start and stop time is displayed

as a result. Where as if I run single item, single level planning with

MD03 for the same material, system runs the planning and proposes the

purchase requisition also for that material.

Is the planning file creation is the solution of the issue...

if it is then how to create the planning file for bulk material (800 no approx). Do we need to do create the planning file again and again, if we want to add the mateail in Re-order point planning

Regards,

Sachin

Former Member
Not what you were looking for? View more on this topic or Ask a question