Production order settlement ?

Dear all

Iam settling a MTO production order in multi stages , in the first confirmation if i settle , my cost of production (cr) , my Inventory accounts ( Dr) .

I consume the confirmed quantity to my sales order , now for my second confirmation if i settle the Cost of production is Debitted , My inventory accounts is splitted in to 2 postings , half the value to Inventory A/c, half the value to Price difference A/c , like wise in my third confirmation , settlement the value gets in to 2 postings

Iam using Moving average price in my material master

kindly suggest me to correct it so as to get only the inventory accounts effected

Regards & thanks in advance