on 08-21-2007 10:45 AM
Hi Experts,
I am creating a production order and come across that there is a shortage of material, a pop up appears displaying "material parts missing". What should I do? What are the ways to find this shortage of material and How to fill this shortage?
Can any one help me out?
Thanks ,
Anukool
Hi,
In the pop-up which appears, choose mateiral shortage you will get the shortage qty of the dependent requirement of that particular material.
In T.code OPJK (checking control) choose your order type & business function 1 & then you can do settings that,
1.If material not available order will not be created.
2.Order will be created even though material is not available.
3.Use decides whether to create an order or not.
For the shortage qty procurement proposals (purchase requisition or planned order is to be created).
Regards,
Senthilkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please send me tcode and other inportant details regarding your problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.