We have created a report through report painter in QA system as per our client requirements. Can some one pls let us know how can we move this report to Production system.
Thanks and Regards
Ravi Kumar
Export and import
GR57
GR58
Normal transport
GCTR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
T.Code: GR37 - export the report with dependent parameters. This will create text file that can be imported in production client T.code: GR38. Before importing the same do ensure that sets if any is assigned in report do exists in production system otherwise it will give an error while importing. once the report is imported in production, create report group group and assign report imported to report group.
hope this helps.
please assign points as a way to say thanks.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ravi,
That should be Workbench request. Difference is
Changes to customisation comes under customisation request. Ex: Changes done in SPRO.
Changes done to programming or reports comes under workbench. Ex: Abap changes (Technical changes).
Hope this will help you.
Pl. assign points if useful.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.