How to prevent usage decision before closing the result recording.I want flow in this order 1.Closing result recording(Valuation) 2.Usage decision 3.Stock posting
Dear,
You cannot do the result recording once the ud has bene done.
If you wish/ need to change specific results, you have to 'reset' the usage decision and that will allow you to reenter the inspection results (Qa12).